Major Overhaul in Poolbeg CCGT focuses on maintaining excellent plant performance in Power Generation

On 22nd april, Poolbeg Combined Cycle commenced a major inspection on CG14. This is a 33,000 equivalent operating hour inspection and represents the most significant type of planned inspection on this type of unit.

The gas turbine scope of work includes a complete disassembly of the unit, rotor removal and destacking on site.

The generator rotor has also been removed for inspection and the rotor has been dispatched to OEM works for 'J Strap' replacement. There is also a very significant amount of balance of plant work programmed, including:

  • Air filterhouse overhaul
  • Diverter damper inspection and repair
  • Expansion joint replacement
  • Stack survey
  • Non Destructive Testing (HRSG & high energy pipework)
  • Boiler feed pump inspection
  • Cooling water system repairs
  • Condenser inspection and repair
  • Switchgear maintenance
  • SI188 inspection and testing work
Three weeks into the overhaul, we are planning to return to service in the first half of June. Thankfully the safety performance has been good to date with only one minor accident reported – weekly safety meetings keep safety as the no. 1 priority.

CG15 and ST16 are also due to some offload late July and early August respectively to undergo major inspection. Costing in excess of €30m across all 3-unit overhauls, this represents the most significant overhaul expenditure in 2006 (after the Moneypoint retrofit project). This expenditure will position Poolbeg CCGT to continue to deliver its excellent levels of availability. EM

  Tony Brennan examines burner hardware

Pictured: Tony Brennan examines burner hardware.


A Siemens contractor closely inspect one of the turbine wheels following its removal.

Pictured: A Siemens contractor closely inspect one of the turbine wheels following its removal.


Kevin Thompson, Martin McConnon and Dave Valentine discuss instrument calibration.