|
Coping with an
ever increasing load
ESB Networks staff plan and manage huge growth loads in the greater Dublin area
We are all familiar with the unprecedented level of development that has taken place around the whole
country and in particular around the greater Dublin area. In the 10 years from 1996 to 2006 there was a
55% increase in load. Claire Quane, HV Planner Dublin Asset Management, tells the story
ESB Networks
In order to provide
electricity to the new
housing estates, industrial
parks, factories etc, staff
in ESB Networks have
been working hard to plan
and manage the current
and future load requirements.
Background
The Greater Dublin Area is
supplied from four Bulk Supply
Points (BSP), 220kV/110kV stations,
Finglas, Inchicore, Ringsend and
Carrickmines, as indicated in
Figure 1. The BSP's provide HV
connections to various 110/38kV
and 110kV/MV stations in discrete
geographical areas in the Greater
Dublin Area; these stations then in
turn feed the load.
Prior to connection large
customers and developers
approach ESB Networks about the
availability of capacity to provide a
connection to their installation.
Such interactions are referred to as
load enquiries. The level of load
enquiries in Dublin is extremely
high with 771MVA of load enquiries currently in the Greater
Dublin Area. It is anticipated that
the vast majority of these
developments will require
connection within the next five to
seven years.
Figure 2 shows the historical
level of load growth in the Dublin
area. In the 10 years from 1996 to
2006 there was a 55% increase in
load. Based on the load enquiries
currently in hand there is
potentially a similar level of load
growth over the next five to seven
years, though it is anticipated that
some of these developments will
not go ahead and others may
develop more slowly than
indicated by developers.
According to Sheila O'Connor,
Manager ESB Network
Investments North, these are
unprecedented levels of growth
which will have a very significant
impact on the HV networks in
Dublin.
Major developers are seeking connections all across the city, and
this will clearly affect the level of
load at each of the BSP's. The
additional load expected at each
BSP is estimated to be as follows:
Finglas: 254MVA
Inchicore: 252MVA
Ringsend: 91MVA
Carrickmines: 174MVA
The existing and expected
level of load in Dublin is such
that capacity on the HV network
will be an issue, hence
significant transmission and
distribution reinforcement will
be required over the coming
years.
Specific Areas
There are a number of areas
where the level of load growth is
particularly large, and
consideration of how these areas
will be accommodated is needed.
By way of example two such
areas are given detailed
consideration below.
1. North Fringe
A very large section of land
stretching from Baldoyle in the
east to the M1 is to be developed;
this area is referred to as the
North Fringe. In addition to the
North Fringe development a
number of other new customers
are seeking connection west the M1 and some existing
customers are increasing their
load requirements. The load is
expected to develop, over the
entire area, from Baldoyle to
Finglas. It is expected that
140MVA of load will require
connection over the coming
years.
The existing HV networks do
not have sufficient capacity to
supply the load that is seeking
connection and both
transmission and distribution
reinforcement is required.
Following an extensive study it
was established that ESB will be
required to reinforce the
network as follows:
- Install a new 110kV circuit
from Finglas 220kV station to
Kilmore 110kV station
- Construct two new 110kV/MV
stations in North Fringe
- Extend the 110kV busbar at
Kilmore 110kV station
- Construct a new 220kV/110kV
station at Balgriffin
2. Ballycoolin
A substantial number of load
enquires and applications have
been submitted in the
Ballycoolin/College Park area,
with load enquiries to date
totalling 46MVA. Further
enquiries of another 30MVA are
under consideration in this area.
The following reinforcements
will be required to be carried out.
- Installation of additional
220kV/110kV transformer
capacity at Finglas BSP
- Installation of a third
110kV/MV trafo at College Park
- Development of a new
110kV/MV station in the area
Reinforcements Required
There are other major load
developments in the Greater
Dublin Area which will require
significant network
reinforcements in the coming
years. Figure 3 identifies the
locations for these
reinforcements.
Currently there are a
number of projects underway
and many more planned to
begin construction over years
to come. The distribution
system will be reinforced as
follows:
- There are five 110kV/MV
stations under construction
at present, shown in red.
Located at Ashbourne,
Balbriggan, Sallynoggin,
Leopardstown and North
Quays
- In addition construction will
begin on six 110kV/MV
stations in 2007, shown in
orange. These stations are at
Ballymun, Pelletstown near
Phoenix Park, Adamstown,
Cookstown, Cherrywood, and
Dardistown at Dublin
Airport for terminal 2
- An additional five 110kV/MV
stations will begin
construction in 2008/2009,
shown in blue. These
stations are at Kilmainham, Trinity College, ParkWest,
North Fringe and Greystones
Conclusion
There has been a significant
upsurge in the level of load
enquires around Dublin in recent
times (770MVA). It is therefore
challenging for ESB Networks to
deliver these stations within the
timescales being indicated. This
will involve very significant HV
work including the development
of HV stations and the
installation of HV underground
cables in congested urban
streets.
Planning Permission is often
given for developments without
consideration of electrical
infrastructure needs. This can
result in the developer not
engaging with ESB until an
advanced stage of the project
which provides an additional
challenge to ESB in providing
connection on time
The relationship between the
transmission and distribution
systems sometimes necessitates
the study of both systems
together to ensure that the
overall best solution is found.
Such studies are complex and
significant engagement and cooperation
between the ESB
Networks and EirGrid is
required. The North Fringe
project is an example of a
successful outcome to such a
joint study.
The level of capital work
planned in the coming years is
challenging in terms of our
ability to deliver on such a major
and complex programme.
However, given the track record
of staff in Network Projects who
have consistently delivered, ESB
Networks is confident of
meeting its commitment to
provide its customers with an
excellent standard of service.
"We are confident in our
ability to deliver on this
challenging work programme,"
says Denis O'Leary, Head of Asset
Management. "This will allow
Dublin to continue to develop as
one of the major capital cities of
Europe."EM
|