![]() | ||||
|
Moneypoint Environmental Retrofit Project
Background
The project started in 2004 and runs until the end of this year. It has three main works streams:
There has been substantial work completed on the project in the last three years. During this period there have been more than three million contractor manhours worked on the MERP site alone, with a peak workforce of 750 contractors. When the existing station staff are added to this figure, as well as the 300 contractors working in the station during overhauls, the total number of personnel entering Moneypoint during peak periods of construction reached as many as 1,300 workers. Current status The change of C&I systems on Units 1 and 3 was completed during major outages in 2006 and 2007, with the change to the C&I systems on Unit 2 taking place during the current 19 week unit outage. These outages have also allowed the tie-in of ducting from the FGD and SCR equipment to the existing plant, as well as allowing the generating plant to be refurbished. The project recently passed some major milestones when the FGDs on Unit 3 and Unit 1 went into SOx abatement mode on Saturday, February 16th and Thursday, March 20th respectively. It is expected that the SCR equipment on these units will go into service in the coming weeks.
FGD and SCR equipment for
Unit 2 is currently under
construction and will enter service
towards the end of this year.
|
![]() Pictured: View of Moneypoint from Kilrush Road.
![]() Pictured: Unit 1 FGD near completion.
![]() Pictured: Unit 2 FGD absorber and baghouse filter.
| |||
| Disclaimer | Privacy | Accessibility | www.esb.ie | |||||