![]() | ||||||||||||
|
Renewable Energy - Wind Generation in Ireland WIND GENERATION in Ireland has seen a dramatic increase in activity in recent years. In response ESB Networks has had to address new issues from both technical and administrative points of view. This article aims to give a flavour of the main aspects.
Background Renewable generators can be
connected at a range of voltages,
depending largely on the MW size
and access to suitable network.
Typically, generators will be
connected as follows:
Generally windfarms are completely unmanned except for routine maintenance visits. Most have sophisticated remote control systems to monitor performance, and this often done by the manufacturers in Denmark or Germany. Wind Turbines: Development of wind
generation in Ireland Up to 2003 applications were being connected in sequence on a "first come, first served" basis. This unplanned process was leading to erratic system development and potential huge inefficiencies in network structure. In addition the sheer volume proposed was about to impact on system stability and was of serious concern to National Grid (TSO). As a consequence, DSO (ESB Networks) and TSO made a joint submission to the Commission for Energy Regulation (CER) proposing a moratorium on connection offers pending a full review of system stability and connection issues. The CER imposed a moratorium from December 2003 to December 2004. During this period, new procedures were developed to address system issues and a new process for handling applications was put in place, essentially a move from individual to a group processing regime. During the moratorium (12 months) the queue of applications increased from 422MW to 2295MW. Both DSO and TSO process applications and make connection offers based on the connection method and established system boundaries. Applicants are free to make their applications to either TSO or DSO. However, depending on the size and suitability of connection methods, the system operators will exchange applications as appropriate. Group processing Renewable Energy Gates 1 and 2
It is anticipated that Gate 2 will result in an additional 1300MW of connection offers between DSO and TSO. The process of invoicing and assessing applications in the first 500MW began in April 2006 following the CER draft direction. Processing and assessing the remainder of applicants will begin following CER's final direction, which is expected in June. The scale of the task in assessing the applications is unprecedented -- over 210 applicants totalling 3000MW must be considered and in a very short timeframe. This represents a processing volume which is 400%- 500% greater than Gate1 and must be completed in a shorter time frame. CER has directed that all successful applicants be identified within 2 months and all offers will be issued within 12 months. The task of identifying successful applicants lies with DSO. Offers of connection will be made by DSO and TSO as appropriate. The Network
Investment Team The coming twelve months will see a further step change in the level of applications for wind connections under Gate 2. This work load will present a considerable challenge to the Wind Generation Team. They will now be lead by Tony Hearne who has recently been appointed as Generation Planning Manager. EM |
![]() Photo of Sandie Madden
![]() Photo of Emma McAleese
| |||||||||||
| Disclaimer | Privacy | Accessibility | www.esb.ie | |||||